Shanghai XXX Electric Co., Ltd. x Odoo ERP full chain upgrade

🏭  Customer Case: Shanghai Certain Electric Co., Ltd. × Odoo ERP Full-Link Upgrade

🔍 ‌Company background

Industry: Electrical Equipment Manufacturing and Engineering Services

Scale: 300+employees, annual revenue of 230 million RMB

Core business: Production of high and low voltage electrical equipment, delivery of industrial automation engineering

🚩 ‌Core pain points (before implementation in 2024)

1.     ‌Production and supply chain disconnect: 30% of orders are delayed in delivery due to material shortages caused by manual scheduling.

2.     ‌Project cost out of control: The actual cost of engineering service projects exceeds the budget by as much as 25%.

3.     ‌Inefficient quality traceability: The average traceability time for product defects is 72 hours, and the customer complaint rate is 18%.

🛠️ ‌Odoo Solution

Module deployment:

·        ‌Production (MRP II): Dynamic Scheduling Engine+Equipment Capacity Visualization Dashboard

·        ‌Project management: Real time collection of labor hours/materials/outsourcing costs

·        ‌Quality Management: Batch Number Tracking+Root Cause Analysis (RCA) Tool Chain

Customized development:

·        PLM system integration: BOM version changes are automatically synchronized to the production module

·        IoT device data center: real-time warning of production line OEE (overall equipment efficiency)

·        Cloud collaboration of engineering drawings: customer approval process shortened from 7 days to 24 hours

📅 ‌Implement milestones

stage

Time node

Key achievements

Requirement diagnosis

2024.01

Sort out 37 pain points in 6 major business departments

Deployment

2024.04

Migration of 150000 pieces of material master data

Stress testing

2024.07

200+concurrent users meet performance standards

Officially launched

2024.10

95% of business processes are paperless

📊 ‌Quantitative income comparison (as of February 22, 2025)

index

Before implementation

After implementation

Improvement range

On-time delivery rate of orders

68%

92%

⬆35%

Inventory holding cost

2300Ten thousand yuan

1700Ten thousand yuan

⬇26%

Project cost deviation rate

±25%

±8%

⬇68%

Quality traceability timeliness

72Hours

4Hours

⬇94%

🌐 ‌Technical architecture diagram

mermaidCopy Code

graph LR 

A(PLM system) -->|BOM data| B(Odoo MRP) 

B --> C[production order] 

C --> D{IoT device} 

D -->|OEE data| E[Warning Center] 

B --> F[Procurement module] 

F --> G[Supplier Collaboration Platform] 

E --> H[BI Decision board] 

Note: The red arrow represents the customized development interface

💬 ‌Customer Testimony

“Odoo's MRP and project management modules enable us to accurately align our production plans with the supply chain, resulting in a significant increase in engineering delivery cost deviation rate from the bottom of the industry to the top 10%.”

—— Chen Lifeng, Director of Electrical Operations at a certain company

🎯 ‌Summary of Case Value

·        ‌Cost controllability: By collecting work order level costs, direct material waste is reduced by 18%.

·        ‌Agile delivery: Equipment capacity utilization rate increased from 65% to 82%, and emergency order response speed increased by 40%.

·        ‌Compliance assurance: ISO quality management processes are 100% digitized, reducing audit preparation cycles by 90%.

 